Multi-Unit Townhome Punch List Completion
Complete punch list resolution for a 12-unit townhome development. We cleared over 150 deficiency items across all units in one coordinated visit, helping the developer meet their occupancy deadline.
The completed 12-unit development in Burnaby
Final kitchen details including cabinet hardware and trim
Bathroom finishing including mirrors and accessories
The Challenge
The developer was three days from occupancy permits with a punch list of 150+ items across 12 units. Multiple trades needed to complete work, but the original subcontractors were unavailable. Items ranged from drywall touch-ups to trim repairs to hardware installation.
Our Solution
We deployed a multi-trade team that systematically worked through all 12 units. By handling drywall, painting, trim, and hardware ourselves, we eliminated coordination delays. All items were completed in two days, giving the developer time for final inspections.
"We use Nookmaster on every townhome project now. They understand the pressure of closing timelines and consistently deliver. One team, one invoice. Exactly what we need."
The Situation
Westside Developments contacted us with an urgent request. Their 12-unit townhome development in Burnaby was days away from scheduled occupancy, but the punch list showed over 150 items still outstanding. Their regular trades were committed to other projects.
Our Solution
We brought in a four-person team with expertise across all the needed trades. Rather than unit-by-unit, we worked trade-by-trade, completing all drywall work first, then painting, then trim, then hardware, maximizing efficiency.
Items Completed
- Drywall patches and touch-ups (47 locations)
- Paint touch-ups and accent wall completion (23 areas)
- Trim installation and repairs (35 pieces)
- Cabinet and door hardware (12 units, 288 pieces)
- Light fixture adjustments (18 fixtures)
- Bathroom accessory installation (12 complete sets)
Result
All 150+ items cleared in two days. Occupancy permits issued on schedule.